Mobilization completed in less than three weeks

Siddis Mariner was made ready for seismic assignments for PXGEO at Green Yard Kleven in August.

The mobilization was carried out in less than 3 weeks and involved the production and installation of a double mezzanine deck for the ROV, several different foundations for equipment and a complete node handling system with all necessary equipment on deck. In addition, we have delivered and installed two ten-tonne deck cranes which we have overhauled and re-certified for ROV operation.

 This was only possible in such a short time with good planning by both shipowners, customer and shipyard, prefabrication, and not least that all departments at the shipyard together with partners have been at full capacity and made an absolutely fantastic effort and a job well done!

This is the second mobilization we are doing for PXGeo, we thank you so much for the assignment and the good cooperation.